top of page

Effective DSO Management — Avoiding €75k Generator Hire
A 25-day DSO outage (in three blocks) was scheduled for a nearby asset connection. With no back-feed planned, the wind farm would need generators to maintain house loads.
Client
N/A
Value
N/A
Location
N/A
Architect
N/A

Challenge
Keep the wind farm energised without generation during a prolonged outage, avoid costly generator hire, and align with DSO safety/operational constraints.

Solution
Negotiated a reduced outage period and an innovative “tail-feed” arrangement with the DSO.
Implemented engineering controls to prevent export while supplying sufficient power for substation/turbine house loads.
Coordinated DSO to bring forward routine station maintenance to maximise outage value.

Outcome
No generators required; ~€75,000 cost avoided. The approach was formalised with the DSO for use in future outages.