EnergyPro assumed management of an operational project and found the site was not reaching Maximum Export Capacity (MEC) at the meter.

Client

N/A

Value

N/A

Location

N/A

Architect

N/A

Export Capacity Analysis — 2% Asset Output Gain

Challenge

Resolve a meter-gate shortfall masked by healthy turbine SCADA data, and persuade stakeholders to investigate when initial OEM feedback indicated “no issue.”

Blue large wave_2-min_edited.png

Solution

Compared potential vs. actual power: turbine SCADA showed no problem; substation metered data showed the gate shortfall.
Procured temporary sub-meters at generators and substation to localise the error.
Root cause: incorrect cable screening in a control unit causing inaccurate CT/VT readings.
Coordinated rectification while keeping OEM engaged.

Blue large wave_2-min_edited.png

Outcome

Correct installation restored; asset output increased by ~2%