Finding & Fixing Planning Compliance Problems

Finding & Fixing Planning Compliance Problems

After acquiring a third-party–managed operational wind farm, the owner discovered significant planning and environmental non-compliances.

Client

N/A

Value

N/A

Location

N/A

Architect

N/A

Finding & Fixing Planning Compliance Problems

Challenge

Multiple concurrent risks: ecology (habitat management, bird/bat monitoring), noise, shadow flicker, and planning/forestry licensing exposures—plus potential legal challenges threatening operations.

Blue large wave_2-min_edited.png

Solution

Prepared and implemented an Operational Stage Environmental Management Plan (OSEMP).
Led ecology monitoring (habitats, vantage point and fatality surveys), noise and shadow-flicker campaigns.
Managed compliance/enforcement submissions and coordinated planning applications and forestry (turbulence/mitigatory habitat) licences.
Provided inputs for legal submissions and responses.

Blue large wave_2-min_edited.png

Outcome

+1% immediate increase in turbine production, validated by post-fix measurements.