Galetech Group Wind Farm

White Hill Wind Farm Project

Galetech Energy Developments Ltd.  received planning permission on  21 November 2023, from ACP  for 7 no. wind turbines with hub height of 104 metres, a rotor diameter of 162 metres and overall tip height of 185 metres in the townlands of The Ridge, Knocknabranagh and Knockbaun, Baunreagh, and Agharue, County Carlow and Coolcullen, Cloneen and Coan East, County Kilkenny and received planning permission on 5th September 2025 from ACP for  110 kilovolt electricity substation, approximately 8.8kilometres of underground electricity line, an electrical control unit and all associated works at Shankill and Ballygorteen, County Kilkenny; and Moanmore, Lackan and Baunreagh, County Carlow.

Wind Farm Output

50.4MW

Turbines

7

Homes Powered

36,000

CO₂ Saved

38,000 tonnes CO₂ /year

Community Fund

Up to €300,000/year

About The Project

Galetech Energy Developments Ltd.  received planning permission on  21 November 2023, from ACP  for 7 no. wind turbines with hub height of 104 metres, a rotor diameter of 162 metres and overall tip height of 185 metres in the townlands of The Ridge, Knocknabranagh and Knockbaun, Baunreagh, and Agharue, County Carlow and Coolcullen, Cloneen and Coan East, County Kilkenny and received planning permission on 5th September 2025 from ACP for  110 kilovolt electricity substation, approximately 8.8kilometres of underground electricity line, an electrical control unit and all associated works at Shankill and Ballygorteen, County Kilkenny; and Moanmore, Lackan and Baunreagh, County Carlow.

Project Milestones

Galetech Group Wave
Galetech Group Team

Community Consultation

We’re here to listen and support our local community.

 

Freephone: 1800 140 240 

 

Email: clo@whitehillwindfarm.ie

 

Book a meeting or contact us down below. 

Layout

The White Hill Wind Farm layout includes sections of Coillte property in its proposal in

addition to other third party lands.  If you have any Coillte related queries, please contact is info@coillte.ie.

Wind Turbine

Galetech Group White Hill Farm Map

Project Updates

September 2025

Planning has been granted for 110kV Electricity Substation 8.8km of underground Electricity Line.

March 2025

Information Flyer 

Galetech Group Wave

FAQs

Community Grants & Fund Activities

From Community Support to Champions: Drumcullen Camogie’s Senior B Title

From Community Support to Champions: Drumcullen Camogie’s Senior B Title

St. Oliver Plunkett NS Visit Old Mill Wind Farm and Build a “Human Turbine”

St. Oliver Plunkett NS Visit Old Mill Wind Farm and Build a “Human Turbine”

A Day of Discovery: Oliver Plunkett’s N.S. Visits Old Mill Wind Farm

A Day of Discovery: Oliver Plunkett’s N.S. Visits Old Mill Wind Farm

Abstract blue and black background with speckled dots and curved edge.

Awards and Certifications

Galetech Group Wave

Your Community. Your Ideas. Our Support.

If you have a project that can make a positive impact - big or small - we’d love to hear from you. Applications are now open for our Community Fund.


Local groups, clubs, and individuals are encouraged to apply.

bottom of page